News & Reviews News Wire MRL and BNSF detour trains as Yellowstone River bridge derailment cleanup progresses (updated)

MRL and BNSF detour trains as Yellowstone River bridge derailment cleanup progresses (updated)

By Bill Stephens | June 27, 2023

The regional railroad does not yet have an estimate for when it will be able to replace the collapsed bridge

Email Newsletter

Get the newest photos, videos, stories, and more from Trains.com brands. Sign-up for email today!

Aerial view of collapsed bridge and railcars in river
Montana Rail Link and BNSF Railway are detouring trains following Saturday’s collapse of an MRL bridge over the Yellowstone River. Jeremy J. Schrader

REED POINT, Mont. — The Montana Rail Link bridge over the Yellowstone River, which collapsed on Saturday, passed inspections in November 2022 and last month, railroad President Joe Racicot said at a unified command news conference on Monday evening.

“We feel confident that this bridge was suitable for stream flows,” Racicot says. A combination of snow melt and heavy rainfall has swollen the Yellowstone River in the area.

“We do invest heavily in our capital infrastructure and this bridge was no exception,” Racicot says.

The century-old former Northern Pacific bridge carries 16 or 17 trains per day, Racicot says, and an eastbound train crossed the span an hour before the 52-car westbound Laurel to Missoula, Mont., local that derailed around 6 a.m. on Saturday.

Officials said it remains unclear which came first: The bridge collapse or the derailment that sent 10 cars into the river.

The Federal Railroad Administration and National Transportation Safety Board are investigating, while the unified command team of officials from Stillwater County Disaster and Emergency Services, the Montana Department of Environmental Quality, the U.S. Environmental Protection Agency, and Montana Rail Link are handling incident response.

With derailment cleanup still under way, Montana Rail Link does not yet have an estimate for how long it will take to replace the bridge that has severed its main line, Racicot says.

The route is a key link for BNSF Railway traffic moving to and from the Pacific Northwest. MRL operates the route under lease from BNSF. The companies reached a deal last year on early termination of the lease, and BNSF expects to take over operations on Jan. 1.

MRL is working with its unions and BNSF to detour its own traffic via BNSF’s former Great Northern Hi-Line, Racicot says.

A BNSF spokesman says the railway is detouring the majority of its MRL overhead traffic via the Hi-Line by running it on its route from Laurel, Mont., to the Hi-Line junction at Shelby, Mont. Some BNSF detours are running on Union Pacific between Hastings, Neb., and Portland, Ore., BNSF says.

“We made some good progress today with cleanup,” Racicot said.

The contents of two tank cars containing sodium hydrosulfide, that were located on the west side of the bridge, have been transferred into stable railcars and moved to safety, the EPA said. Eight railcars on the eastern side of the bridge that did not reach the water have been removed, as well. Four asphalt cars remain on the eastern side of the bridge. These will be removed as cleanup efforts continue, according to the EPA.

State and federal environmental officials remain on scene, and MRL is bringing in environmental cleanup experts.

Ten cars remain in the river, including six loaded asphalt, three carrying molten sulfur, and one car of scrap metal.

EPA officials said water readings are not showing contamination but blobs of asphalt have been showing up downstream. Asphalt is not water soluble and is not anticipated to impact water quality, officials said. Water quality testing results from Saturday show no detectable levels of petroleum hydrocarbons or sulfur and samples continue to be taken and analyzed.

“We have brought in a specialized dive team. They’re going to help us not only assess what’s in the river but also help us secure the cars for removal from the river,” Racicot says.

Note: Updated with BNSF comment at 4:20 p.m. CDT.

8 thoughts on “MRL and BNSF detour trains as Yellowstone River bridge derailment cleanup progresses (updated)

  1. The locomotives pulling the derailed freight train are most likely MRL’s EMD SD70ACe’s.

    Dr. Güntürk Üstün

  2. An old highway bridge that paralleled the railroad bridge – together, they were called the Twin Bridges – was removed in 2021 after the Montana Department of Transportation determined it was in imminent danger of falling. It wasn’t immediately clear when the railroad bridge was constructed or when it was last inspected.

    Dr. Güntürk Üstün

  3. A terrible event that narrowly escaped a large-scale disaster! Of course, the necessary lessons must be learned!

    Dr. Güntürk Üstün

  4. In the 1970’s, BN president Norm Lorentzsen was on his business car when it passed over this bridge and felt it subside; he immediately had dispatchers stop all trains and inspection revealed subsidence due to scour at a pier. This was pre-MRL and I don’t know how much institutional memory of this at MRL or BNSF, but due to this history, it’s very likely this is the cause. There are now techniques to use ground penetrating radar to look for scour during and after flood events and that would be a good preventive measure in the future. I suspect the spans can be salvaged once a restored pier is in place, but the work will have to wait until the river gets to summer level.

    1. In 2013 we had an instance of scouring cause a bridge failure on the CP in Calgary, AB. I remember our mayor tore CP a new one for the perceived lack of safety initiative.

      If that’s what happened here, this is a much worse failure, for the same reason, than the one at CP.

      CP, for the record, had the bridge replaced within a few months, with a whole new pier.

  5. Surprise, so far Builders have not taken any delays between Sandpoint and Shelby. Big question will be how to reallocate BNSF and MRL crews and get those necessary qualified on detour routes.

  6. How true, which came first the collapse or the derailment, both can cause the other.
    Sure going to be a difficult mess to clean up.

You must login to submit a comment