HARTFORD, Conn. — More than five months of midday bus substitutions on the Hartford-Springfield, Mass., route served by Amtrak and CTrail trains are set to end on Monday, Nov. 4, following the completion of several maintenance projects.
An alert on the CTrail website says 10 five round trips — two of Amtrak trains and three operated by CTrail — will resume operation. The revised full schedule is available here; it include some adjustments from those before the work began.
The bus substitutions began in May to allow for work including construction of a new station at Windsor Locks, Conn., featuring high-level platforms and ADA-accessible features; installation of new interlockings, and grade-crossing improvements. That station will open in 2025.
Share this article