Regulatory Swiss freight wagons face new rules: What it means

Swiss freight wagons face new rules: What it means

By Bob Lettenberger | September 19, 2025

New rules raise concerns regarding costs and possible disruption of European rail freight

Email Newsletter

Get the newest photos, videos, stories, and more from Trains.com brands. Sign-up for email today!

Broken rails and ties inside tunnel, with work train in background
Damage from the Aug. 10, 2023, derailment inside the Gotthard Base Tunnel is clearly visible during repair work in November. New Swiss freight wagon regulations are designed to focus on rail safety and help prevent derailments like this. SBB

BERN, Switzerland — The Swiss Federal Office of Transport has announced new regulations for freight wagons in the country. The new regulations include measures such as minimum wheel diameters, more frequent maintenance schedules, and optimized wagon inspections. Operators and fleet owners have until the end of 2025 to comply with the new rules.

The regulations are based on recommendations from the Swiss Transportation Safety Investigation Board following its investigation of the Aug. 10, 2023 Gotthard Base Tunnel derailment. The derailment caused significant damage to the tunnel, closing the trans-Alpine route for nearly 13 months.

Significant provisions in the new regulations include:

Minimum wheel diameter will be 864 mm (34 inches). The broader European standard is 860 mm (33.86 inches).

Wagons will now be technically inspected more frequently with the interval reduced to 50,000 km to 200,000 km (31,068 to 124,274 miles) depending on type of brakes and wheel diameter. Inspections are to include a visual wheel test, a percussion test to detect defects, and a check for damage and overheating.

A valid technical inspection certificate must be maintained to verify regulation compliance before a wagon is operated in Switzerland.

Wheels that have overheated will now have a colored strip applied indicating the thermal stress.

Train drivers will receive instructions on handling practices that will minimize the risk of wheels overheating.

The new regulations are designed to improve rail safety, says the FOT. Wagon owners, however, fear excessive compliance costs and freight moving away from rail to trucks.

The International Union of Wagon Keepers (UIP), a leading industry association, warned that the regulations could lead to a European rail freight traffic meltdown, citing the added costs wagon owners will incur. UIP has described the new requirements as shocking, stating that they could lead to significant economic disruption and added costs for wagon owners. Verband Private Eisenbahnen-Innungen (VPI), a German wagon-owners group, estimates costs could add up to “hundreds of millions annually.”

Verband der verladenden Wirtschaft (VAP), the Swiss wagon-owners’ association, agreed, calling the new regulations as wrong and dangerous. VAP, while stating safety is a top priority, also argued that the regulations may move freight traffic from rail to road, resulting in supply chain bottlenecks.

Concerns have also been raised that the new rules focus solely on freight wagons and do not include infrastructure. The STSB’s report stated failed infrastructure did play a role in the Gotthard Base Tunnel incident. Additionally, wagon owners have expressed concern that the Swiss regulations were enacted unilaterally without discussion across its borders. The European Union Agency for Railways (ERA) already has guidelines for mitigating the risk of broken wheels. Switzerland’s new regulations disregard these measures, raising concerns about the potential for fragmentation within the European rail network, says Travel and Tour World in a recent report.

It is certain that both regulators and wagon owners will be monitoring Swiss rail traffic to gauge the impact of the new rules as the Dec. 31, 2025, implementation deadline approaches.

4 thoughts on “Swiss freight wagons face new rules: What it means

  1. I often hear that “who has the gold makes the rules”. Maybe this is the first time for “who controls the tunnels makes the rules.”

  2. Does the “percussion test to detect defects” involve striking the wheel with a hammer and listening to the sound? In the 70’s while riding the CN Super Continental, I recall hearing car inspectors (car knockers) at major stops such as Edmonton, hitting the wheels and other parts of the trucks to check for cracks. A dull clunk indicated a crack.

    1. Those of us old timers who rode passenger trains before Amtrak and even before all passenger cars were equipped with roller bearings remember well the “car knockers” who checked out the wheels, brakes, and axle boxes. It normally took place at the crew divisions stations where the trains paused longer. I can still recall seeing the lights of the men at night as they made their way down the cars going about their work.

  3. Pet peeve of mine, why must Metric be translated to Imperial (or United States Standard)? If you want to read an article about Switzerland, read it in Metric.

    BTW the translation isn’t always accurate. Usually but not always.